Home › Mechanics Lien Filing › Payment Bond Claims › Montana

You can't lien a Montana public school, county building, state university or city project. On Montana public work, subcontractors and suppliers get paid through the contractor's bond under MCA 18-2-201 to 18-2-208. Two Montana rules trip people up: suppliers to subcontractors have to send a notice within 30 days of their first delivery, and the claim itself is filed with the public owner, not the contractor, within 90 days after the project is accepted. LevelSet Collections prepares and files Montana notices and claims and collects on them, on contingency: no collection, no charge.

Check my bond claim, free

Which Montana jobs are covered

Whenever a board, council, commission, trustees or other body acting for the state, a county, a municipality or another public body contracts for work, it has to require a bond conditioned on the contractor paying laborers, mechanics, subcontractors, material suppliers and anyone supplying the contractor or its subcontractors (MCA 18-2-201). The public body may waive the bond on building or construction projects that cost less than $150,000, and a school district may waive it on projects under $7,500. That takes in public schools, the university system, county courthouses and jails, city buildings, public hospitals, and water and sewer plants.

  • Federal jobs (Malmstrom Air Force Base, VA medical centers, federal courthouses) follow the federal Miller Act instead.

Private hospital, private school or private university? Those can be liened. If you aren't sure who owns the property, send us the address and we'll look it up. If it's private, we file a Montana mechanics lien instead, $199 to $500 all-inclusive.

Montana public bond claim deadlines

StepWhoDeadlineGoes toSection
Notice of a right of action on the securityAnyone supplying materials to a subcontractor30 days after your first delivery to the subcontractorThe contractor, personally or by certified mailMCA 18-2-206
Notice of claim: the amount, the contractor, the surety and a description of the workEvery claimant90 days after the contract is completed and the public body accepts the workPresented and filed with the public body that contracted for the workMCA 18-2-204
Suit on the bondEvery claimantSet by the bond's terms; the statute sets noneCourtMCA 18-2-204

The 30-day supplier notice says it's a notice of a right of action on the security, that you've started delivering, who placed the order, and that the contractor and its bond will be held for the unpaid price. It has to be in substantially the statutory form, and no other kind of notice counts (MCA 18-2-206).

Unpaid on a Montana school, county, city or state job?

Send us the project and your last day on the job. We'll check your 30-day notice and claim dates, free.

Contingency: 10% to 33% of what we recover · No collection, no charge · Texts answered within the hour

A Montana bond claim timeline

Say you're a supplier to a subcontractor on a school district addition. Your first delivery was September 8, 2026, and the school board accepts the finished project on March 1, 2027.

  • October 8, 2026: notice to the prime contractor (30 days after first delivery). This goes out while the job is still running smoothly.
  • May 30, 2027: last day to present and file the notice of claim with the school board (90 days after acceptance).
  • Whatever the bond says: the suit deadline.

How we find the bond

You don't need to know who the surety is before you call us. We request the contract and bond from the public owner, and the notice of claim we file with the public body becomes a public record once it's filed (MCA 18-2-204).

What sinks Montana bond claims

  • Suppliers skipping the 30-day notice because the job was going well.
  • Sending the claim to the contractor but never filing it with the public body.
  • Missing the acceptance date that starts the 90 days.

What we need

  • The project name and location, and who hired you
  • Your contract, purchase order or signed proposal
  • Unpaid invoices and delivery dates
  • Your first and last days on the job

Pricing

Montana bond claims are handled on contingency: 10% to 33% of what we recover, and nothing if we don't collect. No minimum claim size; claims under $1,000 are handled at 50%. Call (469) 694-8003.

Frequently asked questions

Can I file a construction lien on a Montana public school or county building?

No. Montana public property can't be liened. Public bodies have to require a bond on public works contracts (MCA 18-2-201), and you make your claim against that security.

What is the Montana supplier notice on a public job?

If you supply materials to a subcontractor, give the contractor written notice no later than 30 days after your first delivery, personally or by certified mail, in the statutory form (MCA 18-2-206). Without it, you have no right of action on the bond.

What is the deadline for a Montana public bond claim?

Present and file a written notice of claim with the public body that contracted for the work within 90 days after the contract is completed and the public body accepts the work (MCA 18-2-204).

Who gets the Montana notice of claim?

The board, council, commission, trustees or other body acting for the state, county, city, town, district or other public body. Once filed, it's a public record (MCA 18-2-204). We also send a copy to the contractor.

How long do I have to sue on a Montana public bond?

Montana's bond statute doesn't set a suit deadline, so the bond's own terms matter. We get the bond and work from its terms.

What does a Montana bond claim cost?

Nothing up front. We handle bond claims on contingency, 10% to 33% of what we recover. If we don't collect, you don't pay.

This page is general information, not legal advice. LevelSet Collections is not a law firm; we prepare and send notices and claims as agent for the claimant. Deadlines change and depend on the facts of your job. We'll check your dates against the statute before sending anything. Reviewed November 2026.

Related: Payment bond and Miller Act claims · Montana mechanics lien filing · Montana lien deadline calculator · Retainage claims