Every state sets its own clock for mechanics liens, and missing one date can wipe out the claim. This chart puts the four deadlines that matter most side by side for the 18 states where LevelSet Collections files: the preliminary notice, the lien filing deadline for general contractors and for subs and suppliers, and the deadline to sue to enforce the lien. Each row cites the statute and links to our full guide for that state. Click any column heading, or use the Sort by menu, to reorder it.

Not legal advice. This chart is a general summary of private-project deadlines, checked against each state's statute in October 2026. Laws change and many deadlines have exceptions (residential rules, public projects, notices of commencement or completion). Use it as a starting point, not as legal advice for your job.

Mechanics lien deadlines by state, 2026. Sortable.
State page
Georgia Notice to Contractor, only if a Notice of Commencement was filed, from parties with no contract with the GC: later of 30 days after the NOC is filed or 30 days after first furnishing 90 days after last furnishing; copy to owner within 2 business days of filing 90 days after last furnishing; copy to owner within 2 business days of filing Lien action within 365 days after filing the lien, plus a Notice of Commencement of Lien Action within 30 days after filing suit O.C.G.A. §§ 44-14-361.1, 44-14-361.5 Georgia lien guide
Kansas Residential warning statement from subs and suppliers on residential jobs (claims over $250), given before the lien is claimed; no set deadline 4 months after last furnishing (non-residential: up to 5 months with a Notice of Extension filed within the 4 months) 3 months after last furnishing (non-residential: up to 5 months with a Notice of Extension filed within the 3 months) 1 year after the lien statement is filed K.S.A. 60-1102, 60-1103, 60-1103a, 60-1105 Kansas lien guide
Kentucky Notice of intent to lien from parties with no direct contract with the owner: 120 days after last furnishing for claims over $1,000; 75 days for claims under $1,000 or on an owner-occupied 1-2 family home 6 months after last furnishing; mail copy to owner within 7 days of filing 6 months after last furnishing; mail copy to owner within 7 days of filing 12 months after the lien statement is filed KRS 376.010, 376.080, 376.090 Kentucky lien guide
Louisiana Notice of nonpayment from sellers of materials to a sub, on jobs with a notice of contract: 75 days after the last day of the month of delivery. No general preliminary notice for others Notice of contract filed: 60 days after a notice of termination, or 7 months after substantial completion if none. No notice of contract: 60 days after notice of termination or substantial completion Notice of contract filed: 30 days after a notice of termination, or 6 months after substantial completion if none. No notice of contract: 60 days after notice of termination or substantial completion Suit and notice of pendency (lis pendens) within 1 year after filing the statement of claim La. R.S. 9:4804, 9:4822, 9:4823, 9:4833 Louisiana lien guide
Michigan Notice of Furnishing from subs and suppliers: 20 days after first furnishing (a late notice reduces the lien) 90 days after last furnishing; serve within 15 days of recording 90 days after last furnishing; serve within 15 days of recording 1 year after the claim of lien is recorded MCL 570.1109, 570.1111, 570.1117 Michigan lien guide
Minnesota Prelien notice: GC puts it in the written contract or delivers it within 10 days of agreeing to the work; subs and suppliers within 45 days after first furnishing (some projects exempt) 120 days after last furnishing (file and serve) 120 days after last furnishing (file and serve) 1 year after the last item of work in the lien statement Minn. Stat. §§ 514.011, 514.08, 514.12 Minnesota lien guide
Mississippi Notice to Contractor (not single-family homes) from parties with no contract with the GC: 30 days after first furnishing. Single-family homes: Pre-Lien Notice at least 10 days before filing 90 days after last furnishing; copy to owner within 2 business days 90 days after last furnishing; copies to owner and GC within 2 business days 180 days after filing the lien, with a lis pendens Miss. Code Ann. §§ 85-7-405, 85-7-407, 85-7-409 Mississippi lien guide
Missouri Notice to Owner from the original contractor before receiving any payment. Everyone else: notice of intent at least 10 days before filing 6 months after the debt accrues 6 months after the debt accrues 6 months after filing the lien RSMo §§ 429.012, 429.080, 429.100, 429.170 Missouri lien guide
Montana Notice of Right to Claim a Lien: 20 days after first furnishing (45 on some lender-financed jobs), recorded within 5 business days. Not required from a GC hired by the owner, or on commercial or 5+ unit residential jobs 90 days after final furnishing or after a Notice of Completion is recorded 90 days after final furnishing or after a Notice of Completion is recorded 2 years after the lien is filed Mont. Code Ann. §§ 71-3-531, 71-3-535, 71-3-562 Montana lien guide
Ohio Notice of Furnishing, only if a Notice of Commencement was recorded, from parties with no contract with the owner: 21 days after first furnishing 75 days after last furnishing (60 days for 1-2 family homes and residential condos); copy to owner within 30 days 75 days after last furnishing (60 days for 1-2 family homes and residential condos); copy to owner within 30 days Lien lasts 6 years; if the owner serves a notice to commence suit, sue within 60 days Ohio Rev. Code §§ 1311.05, 1311.06, 1311.11, 1311.13 Ohio lien guide
Oklahoma Pre-lien notice from everyone but the GC, to the GC and owner: no later than 75 days after last furnishing. Exempt under $10,000 and on some residential jobs; always required on owner-occupied homes 4 months after last furnishing 90 days after last furnishing 1 year after the lien is filed 42 O.S. §§ 142, 142.6, 143, 172 Oklahoma lien guide
Pennsylvania Notice of Furnishing in the State Construction Notices Directory: 45 days after first furnishing (subs, $1.5M+ searchable projects only). Subs also give a formal notice of intent at least 30 days before filing 6 months after completing the work; serve owner within 1 month of filing 6 months after completing the work; serve owner within 1 month of filing 2 years after filing (judgment within 5 years) 49 P.S. §§ 1501, 1501.3, 1502, 1701 Pennsylvania lien guide
South Carolina Notice to owner from anyone not hired by the owner: no fixed deadline; send early 90 days after last furnishing (serve owner and file) 90 days after last furnishing (serve owner and file) Suit and lis pendens within 6 months after last furnishing S.C. Code Ann. §§ 29-5-40, 29-5-90, 29-5-120 South Carolina lien guide
South Dakota Only if a Notice of Project Commencement was filed: parties with no contract with the GC notify the GC (copy to owner) within 60 days after last furnishing 120 days after last furnishing; mail copy to owner before filing 120 days after last furnishing; mail copy to owner before filing 6 years, or 30 days after an owner's written demand to sue SDCL §§ 44-9-15, 44-9-17, 44-9-24, 44-9-26, 44-9-53 South Dakota lien guide
Texas Notice of claim from subs and suppliers, for each unpaid month: 15th day of the 3rd month after the month of work (residential: 2nd month) 15th day of the 4th month after the month the original contractor's work was completed, terminated or abandoned (residential: 3rd month) 15th day of the 4th month after the last month of work (residential: 3rd month) 1 year after the last day the lien could have been filed (extendable to 2 years from filing by written agreement) Tex. Prop. Code §§ 53.052, 53.056, 53.158 Texas lien guide
Vermont Notice to owner from subs and suppliers: no fixed deadline, but the lien reaches only money still unpaid when the owner gets it 180 days after payment came due for the last work 180 days after payment came due for the last work Suit and attachment within 180 days after recording 9 V.S.A. §§ 1921, 1923, 1924 Vermont lien guide
Virginia Notice to the Mechanics' Lien Agent (1-2 family homes, only if one is named on the permit): 30 days after first furnishing or permit issuance 90 days after the last day of the month of last work, and no later than 90 days after completion 90 days after the last day of the month of last work, and no later than 90 days after completion; written notice to owner Later of 6 months after recording or 60 days after completion or termination Va. Code §§ 43-4, 43-4.01, 43-7, 43-17 Virginia lien guide
Washington Notice to Owner from suppliers, professionals and lower-tier subs: send early; it covers only work in the 60 days before notice (10 days on new homes) 90 days after last furnishing; copy to owner within 14 days 90 days after last furnishing; copy to owner within 14 days 8 months after recording RCW 60.04.031, 60.04.091, 60.04.141 Washington lien guide

Showing all 18 states.

How to read this chart

  • Preliminary notice is the early notice some states require before a lien is valid. Where a state has none for most claimants, the chart says so.
  • Lien filing deadline is the last day to record the lien. "Last furnishing" means the last day you provided labor or materials on the job.
  • Enforcement is the deadline to file a lawsuit to foreclose the lien. If it passes, the lien expires.
  • Sorting by deadline uses the approximate number of days, so you can see which states move fastest.

Working in Texas? Count your exact dates with the Texas lien deadline calculator, or see our pre-lien notice service for early notices in any of these states.

Download the chart

Want a copy for the office or the truck? Download the PDF version (letter size, landscape).

Embed this chart on your site

Free to use on your website, newsletter or intranet. Copy the code below; it shows the full chart and credits the source.

Download PDF

Deadline coming up?

We prepare, file and serve liens in all 18 states, usually within 2 business days. Call (469) 694-8003.

File a lien

Owed money on a job?

Call (469) 694-8003. Liens from $199, filed in about 2 business days. Collections on contingency – no collection, no charge.

Get In Touch