You can't lien an Ohio public school, county building, state university or city project. Ohio gives subcontractors and suppliers two other ways to get paid on a public improvement, and you can use both: a claim against the contractor's payment bond (R.C. 153.54 to 153.56, Ohio's Little Miller Act) and a lien on the public funds still owed to the principal contractor (R.C. 1311.25 to 1311.32). Both start with a notice of furnishing due 21 days after you first show up on the site. LevelSet Collections prepares and serves Ohio notices, public funds liens and bond claims and collects on them, on contingency: no collection, no charge.
Which Ohio jobs are public improvements
Contracts for public improvements with the state or any political subdivision, district, institution or other agency have to carry a bond for the full contract amount, and that bond covers lawful claims of subcontractors, material suppliers and laborers (R.C. 153.54). That takes in public school buildings, state universities, county courthouses and jails, city buildings, public hospitals, and water and sewer plants.
- Ohio Department of Transportation highway contracts aren't covered by section 153.54. Tell us if it's an ODOT job and we'll work from that contract's own bond.
- Federal jobs in Ohio (Wright-Patterson Air Force Base, Defense Supply Center Columbus, VA medical centers, federal courthouses) follow the federal Miller Act instead.
Private hospital, private school or private university? Those can be liened. If you aren't sure who owns the property, send us the address and we'll look it up. If it's private, we file an Ohio mechanics lien instead, $199 to $500 all-inclusive.
Step one: the notice of furnishing (21 days)
If your contract isn't directly with the principal contractor, serve a notice of furnishing on the principal contractor within 21 days after you first perform labor or furnish materials on the site, in the form set by R.C. 1311.261. Laborers don't need one. For bond rights, the notice applies to subcontractors and suppliers whose labor or materials cost more than $30,000 (R.C. 153.56(C)).
A late notice isn't fatal, but it only protects labor and materials from 21 days before it was served onward (R.C. 153.56(D), 1311.261). Serve it on day 60 and the first five-plus weeks of work are uncovered. The principal contractor and your subcontractor have to give you the name and address of the public authority and the principal contractor when you sign up (R.C. 1311.261), so ask for them on day one.
Ohio public claim deadlines
| Step | Deadline | Goes to | Section |
|---|---|---|---|
| Notice of furnishing (if your contract isn't with the principal contractor) | 21 days after you first furnish on the site | Principal contractor | R.C. 1311.261; 153.56(C) |
| Public funds lien affidavit | 120 days after your last labor or material | The public authority (or the representative named in its notice of commencement) | R.C. 1311.26 |
| File a copy of the affidavit for priority | 30 days after serving the public authority | County recorder where the job is | R.C. 1311.29 |
| Suit on a public funds lien after a notice to commence suit | 60 days after the notice is served on you | Court | R.C. 1311.311 |
| Bond claim: statement of amount due | After you furnish, and no later than 90 days after the contract is completed and the improvement accepted | The sureties on the bond | R.C. 153.56(A) |
| Earliest bond suit | 60 days after the statement is furnished | R.C. 153.56(B) | |
| Last day to sue on the bond | One year from acceptance of the public improvement | Court | R.C. 153.56(B) |
Unpaid on an Ohio school, county, city or state job?
Send us the project and your last day on the job. We'll check your notice of furnishing, public funds lien and bond claim dates, free.
Contingency: 10% to 33% of what we recover · No collection, no charge · Texts answered within the hour
The Ohio public funds lien
The affidavit states the amount due and unpaid, the dates of your last labor and last material, all credits and setoffs, and your post-office address (R.C. 1311.26). Once the public authority receives it, it has to detain the claimed amount from what it still owes the principal contractor and hold it in escrow (R.C. 1311.28). It won't detain anything for a claimant who was required to serve a notice of furnishing unless a copy of that notice comes with the claim, which is one more reason the 21-day notice matters.
The public authority serves the principal contractor with a copy of the affidavit, and the principal contractor has 20 days to dispute it. If you furnished to a subcontractor rather than the principal contractor, you also give that subcontractor a copy within 20 days after serving the public authority (R.C. 1311.31). Filing a copy with the county recorder within 30 days gives you a preference over claimants who haven't filed (R.C. 1311.29).
An Ohio public claim timeline
Say you're a supplier to a subcontractor on a school district job. Your first delivery to the site was September 8, 2026, your last was November 20, 2026, and you're owed for the last two months.
- September 29, 2026: notice of furnishing to the principal contractor (21 days after first delivery).
- March 20, 2027: last day to serve the public funds lien affidavit on the school district (120 days after last delivery). We serve it well before that, while the district still owes the principal contractor money.
- 30 days after serving the affidavit: file a copy with the county recorder.
- Within 90 days after the school district accepts the project: statement of amount due to the sureties on the bond. Suit on the bond can follow 60 days later and has to be filed within one year of acceptance.
How we find the bond and the contract
You don't need to know who the surety is before you call us. We request the contract, the bond and any notice of commencement from the public authority under the Ohio Public Records Act, which requires public records to be promptly prepared and made available, and copies provided within a reasonable period of time (R.C. 149.43).
What we need
- The project name and county, and who hired you
- Your contract, purchase order or signed proposal
- Your first and last days on the site
- Unpaid invoices, and a copy of any notice of furnishing you already sent
Pricing
Ohio bond claims and public funds liens are handled on contingency: 10% to 33% of what we recover, and nothing if we don't collect. No minimum claim size; claims under $1,000 are handled at 50%. Call (469) 694-8003.
Frequently asked questions
Can I put a mechanics lien on an Ohio public school or county building?
No. Ohio public property can't be liened. Ohio gives you two other remedies on public improvements: a claim against the contractor's payment bond (R.C. 153.56) and a lien on the public funds still owed to the principal contractor (R.C. 1311.26).
What is the Ohio notice of furnishing on a public job?
A notice to the principal contractor from subcontractors and suppliers who don't have a direct contract with it, due within 21 days after first furnishing on the site (R.C. 1311.261). For bond rights it applies when your labor or materials cost more than $30,000 (R.C. 153.56(C)). A late notice still works, but only for work from 21 days before it was served onward.
What is the deadline for an Ohio public funds lien?
The sworn affidavit has to be served on the public authority within 120 days after your last labor or material (R.C. 1311.26). A copy should be filed with the county recorder within 30 days after that for priority (R.C. 1311.29).
What is the deadline for an Ohio payment bond claim?
Furnish the sureties a statement of the amount due no later than 90 days after the contract is completed and the public improvement is accepted. Suit can't be filed until 60 days after that statement and has to be filed within one year of acceptance (R.C. 153.56).
What is a notice to commence suit?
The public authority, the principal contractor or a subcontractor can serve you a notice to commence suit on a public funds lien. You then have 60 days to sue, or the affidavit is void and the funds are released (R.C. 1311.311).
What does an Ohio bond claim or public funds lien cost?
Nothing up front. We handle Ohio public claims on contingency, 10% to 33% of what we recover. If we don't collect, you don't pay.
This page is general information, not legal advice. LevelSet Collections is not a law firm; we prepare and send notices and claims as agent for the claimant. Deadlines change and depend on the facts of your job. We'll check your dates against the statute before sending anything. Reviewed November 2026.
Related: Payment bond and Miller Act claims · Ohio mechanics lien filing · Ohio lien deadline calculator · Retainage claims