You can't lien a South Dakota public school, county building, state university or city project. On South Dakota public work, subcontractors and suppliers get paid through the contractor's bond under SDCL chapter 5-21. South Dakota works differently from most states: there's no pre-claim notice, but the public owner gets the first six months after completion and final settlement to sue on the bond, and claimants sue after that, in the owner's name. LevelSet Collections handles South Dakota bond claims and collects on them, on contingency: no collection, no charge.

Check my bond claim, free

Which South Dakota jobs are covered

Before starting work on a public improvement, the contractor has to furnish a bond of at least the contract price, covering faithful performance and prompt payment of everyone supplying labor or material for the work (SDCL 5-21-1). The public owner may waive it when the bid doesn't exceed the bid limit set under SDCL 5-18A-14 for public improvements. That takes in public schools, state universities, county courthouses and jails, city buildings, public hospitals, and water and sewer plants.

  • No bond posted? The public owner is liable to pay for the labor and material itself, but that action has to be brought within 90 days after the work is accepted (SDCL 5-21-2).
  • Federal jobs (Ellsworth Air Force Base, VA medical centers, federal courthouses) follow the federal Miller Act instead.

Private hospital, private school or private university? Those can be liened. If you aren't sure who owns the property, send us the address and we'll look it up. If it's private, we file a South Dakota mechanics lien instead, $199 to $500 all-inclusive.

South Dakota public bond claim deadlines

StepDeadlineSection
Public owner's exclusive window to sue on the bondSix months after completion and final settlement of the contractSDCL 5-21-6
Claimant's own suit (in the public owner's name, with affidavit and certified copy of the contract and bond)After those six months, and within one year after themSDCL 5-21-6
Joining another claimant's suitWithin one year after completion of the work, and not laterSDCL 5-21-6
Claim against the public owner when no bond was required90 days after acceptance of the workSDCL 5-21-2

Only one suit can be brought on the bond, in circuit court for the county where the contract was performed, and other claimants file into it (SDCL 5-21-6). Notice of the suit goes to known creditors and runs in the local newspaper (SDCL 5-21-8).

Unpaid on a South Dakota school, county, city or state job?

Send us the project and your last day on the job. We'll find the bond and track the settlement dates, free.

Contingency: 10% to 33% of what we recover · No collection, no charge · Texts answered within the hour

A South Dakota bond claim timeline

Say you're a subcontractor on a school district addition, and the district completes final settlement with the prime contractor on March 1, 2027.

  • March 1 to September 1, 2027: the school district's window to sue on the bond. If it does, you can intervene in that suit.
  • After September 1, 2027: if no suit was filed, the claimant can bring its own suit in the district's name after applying with an affidavit and a certified copy of the contract and bond. We gather those documents and track the date.
  • September 1, 2028: outside date for that suit (one year after the six months).

Meanwhile, we work the claim directly with the prime contractor and the surety. Most bond claims get paid long before anyone has to file.

How we find the bond

You don't need to know who the surety is before you call us. On application with an affidavit that you furnished labor or material and weren't paid, the public owner furnishes a certified copy of the contract and the bond (SDCL 5-21-6).

What sinks South Dakota bond claims

  • Losing track of final settlement, which starts every clock.
  • Missing the one-year window to join a suit someone else filed.
  • On unbonded jobs, missing the 90-day window after acceptance.

What we need

  • The project name and location, and who hired you
  • Your contract, purchase order or signed proposal
  • Unpaid invoices and delivery dates
  • Your first and last days on the job

Pricing

South Dakota bond claims are handled on contingency: 10% to 33% of what we recover, and nothing if we don't collect. No minimum claim size; claims under $1,000 are handled at 50%. Call (469) 694-8003.

Frequently asked questions

Can I file a mechanics lien on a South Dakota public school or county building?

No. South Dakota public property can't be liened. Before starting a public improvement, the contractor has to furnish a bond of at least the contract price that includes prompt payment of everyone supplying labor or material (SDCL 5-21-1).

Is there a notice deadline for a South Dakota public bond claim?

The bond chapter doesn't require a pre-claim notice. Instead, it controls when and how suit is brought: the public owner gets the first six months after completion and final settlement.

How do I sue on a South Dakota public bond?

If the public owner hasn't sued within six months after completion and final settlement, you apply with an affidavit that you furnished labor or material and weren't paid, get a certified copy of the contract and bond, and sue in the public owner's name in circuit court in the county where the work was done (SDCL 5-21-6).

How long do I have to sue?

The suit has to be filed within one year after that six-month period. Other claimants can join within one year after completion of the work, and not later (SDCL 5-21-6).

What if the public owner never required a bond?

The public owner is liable to pay for the labor and material, but the action has to be brought within 90 days after acceptance of the work (SDCL 5-21-2).

What does a South Dakota bond claim cost?

Nothing up front. We handle bond claims on contingency, 10% to 33% of what we recover. If we don't collect, you don't pay.

This page is general information, not legal advice. LevelSet Collections is not a law firm; we prepare and send notices and claims as agent for the claimant. Deadlines change and depend on the facts of your job. We'll check your dates against the statute before sending anything. Reviewed November 2026.

Related: Payment bond and Miller Act claims · South Dakota mechanics lien filing · South Dakota lien deadline calculator · Retainage claims

Unpaid on a South Dakota public job?

Bond claims on contingency, 10% to 33% of what we recover. Call (469) 694-8003.

Start a bond claim