You can't lien a Vermont public building, school, town project or state highway. Vermont's public-project rules are thinner than most states'. Only Agency of Transportation construction projects have a statutory payment bond claim procedure (19 V.S.A. § 10). On schools, town buildings and other public work, whatever payment bond the job carries, and the contract, set the rules. LevelSet Collections handles Vermont bond claims and collects on them, on contingency: no collection, no charge.

Check my bond claim, free

Agency of Transportation projects

Contractors on Agency of Transportation construction projects have to file a performance bond and an additional surety bond for the benefit of labor, material suppliers and others. The labor and material bond covers unpaid claims for materials, labor, equipment rental, professional services and similar items (19 V.S.A. § 10(8), (9)). The Secretary may waive each bond on contracts of $250,000 or less.

StepDeadlineGoes toSection
Sworn statement of your claim90 days after the State's final acceptance of the projectFiled with the Secretary of Transportation19 V.S.A. § 10(9)(B)
Petition to enforce the claimOne year after filing the claimSuperior Court, in the name of the Secretary, with notice to the contractor, the surety and the Secretary19 V.S.A. § 10(9)(B)

Unpaid on a Vermont state, town or school job?

Send us the project and your last day on the job. We'll find the bond and check your claim dates, free.

Contingency: 10% to 33% of what we recover · No collection, no charge · Texts answered within the hour

Schools, town buildings and other public work

Outside Agency of Transportation projects, Vermont doesn't have a statute that sets bond claim deadlines. If the public owner required a payment bond, the bond's own terms set who can claim, the notice and the suit deadline. Bond forms often count from your last day on the job, so the first thing we do on any Vermont public job is get a copy of the bond and the contract.

  • Federal jobs (VA medical center, federal courthouses, border stations) follow the federal Miller Act instead.

Private hospital, private school or private university? Those can be liened. If you aren't sure who owns the property, send us the address and we'll look it up. If it's private, we file a Vermont mechanics lien instead, $199 to $500 all-inclusive.

A Vermont transportation bond claim timeline

Say you're a supplier to a subcontractor on a state highway bridge project, and the State gives final acceptance on March 1, 2027.

  • May 30, 2027: last day to file the sworn statement of claim with the Secretary of Transportation (90 days after final acceptance).
  • One year after filing: last day to bring the petition in Superior Court.

How we find the bond

You don't need to know who the surety is before you call us. We request the contract and bond from the Agency of Transportation, the town or the school district under Vermont's Public Records Act.

What sinks Vermont public claims

  • Assuming the transportation rules apply to a school or town building job.
  • Missing the State's final acceptance, which starts the 90 days on transportation jobs.
  • Never getting the bond on non-transportation jobs, so its deadlines go unnoticed.

What we need

  • The project name and location, and who hired you
  • Your contract, purchase order or signed proposal
  • Unpaid invoices and delivery dates
  • Your first and last days on the job

Pricing

Vermont bond claims are handled on contingency: 10% to 33% of what we recover, and nothing if we don't collect. No minimum claim size; claims under $1,000 are handled at 50%. Call (469) 694-8003.

Frequently asked questions

Can I file a contractor's lien on a Vermont public building?

No. Public projects can't be liened, so on public work you look to the contractor's bond and the contract.

Does Vermont have a Little Miller Act?

Only for Agency of Transportation construction projects. There, contractors file an additional surety bond for the benefit of labor, material suppliers and others (19 V.S.A. § 10(9)). For other public projects, the bond and contract terms control.

What is the deadline on a Vermont transportation bond claim?

File a sworn statement of your claim with the Secretary of Transportation within 90 days after final acceptance of the project, then bring a petition in Superior Court within one year after filing the claim (19 V.S.A. § 10(9)).

When can the Agency of Transportation waive the bond?

The Secretary may waive the labor and material bond on contracts of $250,000 or less (19 V.S.A. § 10(9)).

What about school, town and state building jobs?

No Vermont statute sets a bond claim procedure for those. If there's a payment bond, its terms set the notice and suit deadlines, so we get the bond first.

What does a Vermont bond claim cost?

Nothing up front. We handle bond claims on contingency, 10% to 33% of what we recover. If we don't collect, you don't pay.

This page is general information, not legal advice. LevelSet Collections is not a law firm; we prepare and send notices and claims as agent for the claimant. Deadlines change and depend on the facts of your job. We'll check your dates against the statute before sending anything. Reviewed November 2026.

Related: Payment bond and Miller Act claims · Vermont mechanics lien filing · Vermont lien deadline calculator · Retainage claims

Unpaid on a Vermont public job?

Bond claims on contingency, 10% to 33% of what we recover. Call (469) 694-8003.

Start a bond claim