You can't lien an Oklahoma public school, county building, state university or city project. On Oklahoma public work, subcontractors, suppliers and equipment rental companies get paid through the contractor's bond under 61 O.S. §§ 1 and 2, Oklahoma's Little Miller Act. The rules are short: one 90-day notice if your contract is with a subcontractor, and a one-year deadline to sue. LevelSet Collections prepares and sends Oklahoma bond claims and collects on them, on contingency: no collection, no charge.
Which Oklahoma jobs are covered
Before a contract over $100,000 is awarded to build or repair a public or private building, structure or improvement on public real property, the contractor has to furnish a bond for at least the contract amount (61 O.S. § 1). That takes in public school buildings, state universities and CareerTech campuses, county courthouses and jails, city buildings, public hospitals, and water and wastewater plants. It also covers a private building on public land.
- What the bond covers: what the contractor owes subcontractors and suppliers of labor, materials, machinery or equipment rental, and equipment repair or parts (61 O.S. § 1).
- Construction manager at risk jobs: when an at-risk construction manager or a trade contractor posts the payment bond, only parties with a direct contract with whoever posted that bond can claim on it (61 O.S. § 2(B)(2)). Whose bond you claim on matters.
- Federal jobs in Oklahoma (Tinker Air Force Base, Fort Sill, Vance and Altus Air Force Bases, McAlester Army Ammunition Plant, VA medical centers) follow the federal Miller Act instead.
Private hospital, private school or private university? Those can be liened. If you aren't sure who owns the property, send us the address and we'll look it up. If it's private, we file an Oklahoma mechanics lien instead, $199 to $500 all-inclusive.
Oklahoma bond claim deadlines
| Step | Who | Deadline | Goes to | Section |
|---|---|---|---|---|
| Written notice: the amount claimed and who you furnished to | Anyone whose contract is with a subcontractor, not the contractor that posted the bond | 90 days after your last labor or material | The contractor, with a copy to the surety | 61 O.S. § 2(B)(1) |
| Last day to sue on the bond | Every claimant | One year after your last labor or material | Court | 61 O.S. § 2(A) |
| Extended suit deadline | A claimant who filed a claim on the bond within that first year | Two years after your last labor or material | Court | 61 O.S. § 2(A) |
The notice goes by registered or certified mail, postage prepaid, to the contractor at a place where it keeps an office or does business, with a copy to the surety (61 O.S. § 2(B)(1)). It has to state the amount claimed with substantial accuracy and the name of the party you furnished to or worked for.
Unpaid on an Oklahoma school, county, city or state job?
Send us the project and your last day on the job. We'll find the bond and check your claim dates, free.
Contingency: 10% to 33% of what we recover · No collection, no charge · Texts answered within the hour
An Oklahoma bond claim timeline
Say you're a supplier to a subcontractor on a school district gym, and your last delivery was November 20, 2026.
- February 18, 2027: written notice to the prime contractor and the surety (90 days after last delivery).
- November 20, 2027: last day to sue on the bond (one year after last delivery).
- November 20, 2028: the outside suit date if a claim on the bond was filed within the first year.
If your contract is directly with the prime contractor, no 90-day notice is required by the statute, but the one-year suit clock still runs from your last day on the job. If the deadline lands on a weekend or holiday, don't count on extra days. We mail before it.
How we find the bond
You don't need to know who the surety is before you call us. The bond is filed with the agency, school district or city that awarded the contract, and the officer holding it has to give a copy to anyone claiming rights under it (61 O.S. § 2(A)). We also request the contract and bond under the Oklahoma Open Records Act, which requires public bodies to provide prompt, reasonable access to their records (51 O.S. § 24A.5).
What sinks Oklahoma bond claims
- Sending the 90-day notice to the prime contractor but not the surety.
- Counting the 90 days from the last invoice instead of the last day you worked or delivered.
- Claiming on a construction manager's bond when your contract was with someone else.
- Letting the one-year suit deadline pass while the prime contractor keeps promising payment.
What we need
- The project name and city, and who hired you
- Your contract, purchase order, rental agreement or signed proposal
- Unpaid invoices
- Your last day on the job
Pricing
Oklahoma bond claims are handled on contingency: 10% to 33% of what we recover, and nothing if we don't collect. No minimum claim size; claims under $1,000 are handled at 50%. Call (469) 694-8003.
Frequently asked questions
Can I file a mechanics lien on an Oklahoma public school or county building?
No. Oklahoma public property can't be liened. On contracts over $100,000 for work on public real property, the contractor has to post a bond that covers payment to subcontractors and suppliers (61 O.S. § 1), and you make your claim against that bond.
What is the deadline for an Oklahoma bond claim notice?
If your contract is with a subcontractor and not with the contractor that posted the bond, written notice has to go to the contractor and the surety within 90 days after your last labor or material, by registered or certified mail (61 O.S. § 2(B)).
Do I need to send notice if my contract is with the prime contractor?
The 90-day notice in 61 O.S. § 2(B) applies to claimants who contracted with a subcontractor. If your contract is with the prime, the statute doesn't require it, but you still have the one-year suit deadline.
How long do I have to sue on an Oklahoma public bond?
One year from your last labor or material. If a claim on the bond is filed within that year, the deadline stretches to two years from your last labor or material (61 O.S. § 2(A)).
Does the bond cover equipment rental?
Yes. The bond covers what the contractor owes subcontractors and suppliers of labor, materials, machinery or equipment rental, and equipment repair or parts (61 O.S. § 1).
What does an Oklahoma bond claim cost?
Nothing up front. We handle bond claims on contingency, 10% to 33% of what we recover. If we don't collect, you don't pay.
This page is general information, not legal advice. LevelSet Collections is not a law firm; we prepare and send notices and claims as agent for the claimant. Deadlines change and depend on the facts of your job. We'll check your dates against the statute before sending anything. Reviewed November 2026.